Running Track Refurb Works Begin

As some of you may have noticed, work has started on the running track. This is part of a £1M refurb which includes replacement of the synthetic surface to the running track, installation of a drainage system to the infield and new LED floodlights which have already been installed.

Things are going to plan so far. The weather has been good and the works are expected to finish at the end of May 2016.

A temporary entrance and track has been set up near the Hornsey Gate Entrance where all deliveries and contractors must enter. Contractors should always be using hazard lights.

There has been some damage to the edge of the park which has already been noted. The contractor will be obliged to reinstate all damage caused and put back to original state.